Free tool · Ontario Construction Act
Ontario Holdback Dates
Estimate when holdback must be released on a contract under Ontario's Construction Act.
Contract
Annual releases
No annual releases: substantial performance comes before the contract's first anniversary in 2027.
Substantial performance release
Send me the PDF
How these dates are worked out
- Annual releases fall on each anniversary of the start date from 2027 until substantial performance. Form 6 must be published within 14 days; these dates assume it's published on the last day allowed.
- Holdback can be paid from day 60 after publication and must be paid by day 74. Dates are moved off weekends and Ontario statutory holidays: the Form 6 deadline and opening day move later, the due date moves earlier. A moved date says so under its label.
- Substantial performance is estimated at the end date minus 3% of the contract's length, rounded to whole months (at least one).